Hebron Community Calendar

July 2024

Sun Mon Tue Wed Thu Fri Sat
1
2
  • Food Share Van - Red…
  • Zoning Board of Appe…
3
4
  • All Town Offices and…
  • Celebrate July 4th -…
5
6
7
8
9
10
  • Public Building Comm…
  • CANCELLED Charter Re…
11
12
13
14
15
16
  • Food Share Van - Red…
17
18
19
20
21
22
  • Democratic Town Comm…
  • Economic Development…
  • Republican Town Comm…
23
24
25
26
27
28
29
30
31
Upcoming Events

Development Process

PRE-APPLICATION PROCESS
Town Planner and Staff
Application Determination
• Special Permit Application •
• Subdivision/Re-subdivision Application •
• ZBA •
• Inland Wetlands •
• State & Other •

APPLICATION SUBMITTAL
Application Distribution For Staff Review
• ZBA (if necessary) •
• Inland Wetlands •
• Special Permit/Subdivision •
• Other •

STAFF REVIEW
Town Engineer Review
Fire Marshal Review
Town Sanitarian Review
Town Planner Report

LOCAL AGENCY APPROVAL
(If Necessary)
Wetlands Approval
WPCA Approval
Zoning Board Of Appeals Approval

STATE AGENCY APPROVAL
(If Necessary)
Conndot Review
DEP
DHS
DPUC
Regional Planning Agency

PLANNING & ZONING RECEIPT
Hearing Date Set
or
Administrative Approval
• Max Time: 65 Days •

PUBLIC HEARING
Wetland Approval In Place
• Max Time: 30 Days •

APPLICATION DECISION
Approval/Denial
• Max Time: 65 Days •

FILING WITH TOWN CLERK
Bond In Place

BUILDING PERMIT APPLICATION
• Max Time: 30 Days •

CERTIFICATE OF OCCUPANCY
As-Built Survey Submitted
Certificate of Occupancy Issued
• Max Time: 10 Days •

COMPLETED PROJECT
Bond Release